|
January
30/04 Report
9:30 am
Present:
| Members |
| Merulla |
| Ferguson |
| Collins |
| McCarthy |
| Braden |
| Mitchell |
| Bruckler |
| Jackson in 11:17 |
| |
|
Non Members
|
| McHattie |
| Pearson |
Meeting
began at 9:44 am. Seven new items were added to the agenda. Collins
led decision to receive those for a future agenda. They included
a report calling for a 15 cent transit fare hike. The seven items
are:
- information
item on $809K increase required by changes to Ontario Municipal
Act
- recommendation
for approval of user fee increases from Operations and Maintenance
division including parks, cemeteries, waste disposal, tree trimming,
marina slip rentals, etc.
- recommendation
for transit fare increases in 2004 and 2005
- recommendation
for $1,157,370 new spending in relation to 'work accommodation'
- information
item on winter control budget
- amendments
to budget for $34 million in roads and storm sewer capital worksamendments
to budget for recycling program
Eight
sets of overheads distributed covering various parts of Public
Works. Only 5 were completed. Remaining ones moved to next meeting
were Fleet and Facilities, Waste Management, and Capital Planning
and Implementation.
City
Manager Robertson began the budget presentation and noted that
this was part of ending the situation of "artificial budgets"
followed in the past. Followed by Peter Crocket, head of Public
Works who presented the department overview.
This
is a massive department covering transit, parks, water and wastewater,
roads (including Red Hill), waste management, cemeteries, horticulture,
traffic operations, forestry and operations and maintenance. It
has 1762 employees. Total operating budget in 2003 was $131 million.
Net increase is $21.385 million. The biggest item is $16 million
for winter and summer roads maintenance, $7.4 million in employee
costs $700K for OMERS and $600K for benefits), $3.7 million in
fuel and energy costs (extra $1.3M for hydro, $1M for heating
fuel, $600K for street lighting and traffic signals), $2.5 million
contractual costs (rent, waste contracts as a result of increased
tonnage, DARTS contract, taxiscrip), $2.3 million vehicle/equipment
(this is contribution to reserves). Also $1M for insurance (blamed
on 9/11 effects). There were also $824K in phantom revenues ("there's
been a lot of discussion over a number of years about phantom
revenues" "We've made sure this year that those are
all taken out of our 2004 budget" Some of this correction
has been phased in over several years). They anticipate an extra
$7 million in cost recoveries which offsets some of these increases.
Percent increase sought is 17.9%.
Vehicle
reserves underfunded. Need to get to $7.4M per year as a regular
contribution to make it sustainable. They spend a total of $1.139
million on consultants for operation, plus $12 million for consultants
for capital projects. $49.6 million is for contractual costs.
Two
major enhancements: $809K as a result of municipal act changes
- requirement for road patrol year round, currently only provided
during the winter; also must now do traffic counts (these were
largely abandoned in 1999-2000). Also need $1.1M for "work
accommodation" - essentially covering for employees who are
on light work as a result of injuries (eg 5 transit drivers at
this point; 13 collection staff in waste). In some areas work
accommodation "ratio is as high as 1 in 6". Plan to
move people through work accommodation faster.
Reductions
include winter control where there was a $9 million overrun last
year ($12M to $21M). They are proposing a "cut" of $4.7M
(but this is still $4.3M higher than last year). No reserves left
at end of 2003. Should have "somewhere between $6 and $10M"
in reserve. Hoping $16M will represent the new average costs,
but represents a risk.
Savings
of $1.3M in restructuring planned in 2004. Transit fare increase
to generate $362K ("assumes that part of the budget will
be approved by the end of February so that we can do the proper
notification
anything later than that will have an impact
on our revenue".)
Consulting
budget of $13.1M divided between capital ($12M) and operating.
"Used for a variety of things, whether its environmental
assessment work, whether it's a lot of the infrastructure analysis
and development of our capital budge
geotechnical"
"Consultants are used from a perspective of specialized expertise
and they of course are used from a volume perspective. If we were
to eliminate consultants or drastically reduce them, we either
don't do the work or we'd have to increase staff substantially
to deliver the work." The $12M allocated to capital is based
on a percentage of the total capital budget. Design work, contract
admin and management. "I do not have the design and construction
management staff to be able to deliver the capital program that
is before you without a substantial use of consultants."
"We deliver the capital program, I believe it is about 60%
in-house and 40% using consultants".
Contractual
costs are $49.6M. Waste collection, bluebox, landfill sites operated
by contractors, "we use contractors significantly on the
winter control side, primarily for cleanup as opposed to initial
response". "We do not own a bobcat, for example, we
contract all of our bobcat services for snow removal". Road
spill cleanup also contractual. Maintenance contracts for "electrical,
mechanical, plumbing, air conditioning, heating and ventilation
involved in operating some 700 facilities". "Very extensive
use of various cleaning contracts".
Mitchell:
How much of these increases are actual compared to inter-departmental
transfers? Crockett doesn't really answer. "Reason we do
this is to ensure that we know what our programs cost". Mitchell
asks what it costs staff to do the internal transfers.
Mitchell: increase in roads and winter maintenance. When we first
amalgamated we pulled $5M out of this section of the budget, now
we're putting $16M back in. Crockett doesn't have comparative
figures. We did reduce winter control by $3M in 2001. "We
did pull $3 million out of winter control in 2001. And over and
above that we also found an issue with respect to the material
costs that because of the way things were transferred between
the region and the various municipalities, that got lost in the
translation as we combined all of the budgets and that totalled,
I believe, about $3 million. We are incorporating some of that
back. Some of it is in terms of cost tracking, some of it quite
frankly if I had to do all over again I would have waited for
three years before we did what we did simply because the
Based on the best available information at the time it made sense
to do what we did. As we got better information and we've got
better data we're finding that we have significant variances,
and that's been our problem over the course of 2003."
Mitchell:
"Couple of rural roads paved this year, paved with 8 inches
of asphalt that we just can't afford to do that style of thing
at this time." Question: "How come we're getting greater
than a 10% increase in contractual costs over one year?"
Crockett: Being driven by a lot of things. Example: "cost
with respect to waste management. As our community grows and our
road system grows, as our storm system grows, our contractual
costs increase greater than inflation simply because we're managing
more system
much of what we do is based on the number of
units, not just the unit cost". Mitchell says growth should
increase revenues to offset this. Crocket responds: "As things
work through in terms of new development going in, we are providing
the service
long before it shows up on our assessment rolls.
And as a result of that we're providing the service long before
we're getting the revenue". "The other side of it too,
and we all know this, is that residential doesn't pay all the
costs of the services that it gets, that we are very dependent
on commercial/industrial revenue increases as well, and of course,
we haven't been getting those lately either."
Mitchell:
Issue of cleaning up because of contractors doing poor job. "Yesterday
at about quarter to three we ploughed in Tapleytown school, right
full, just before the buses got there. So the police had to come,
and they had to load the students out on the road, all because
somebody didn't think enough and ploughed in the entrance to the
school 15 minutes before the buses were to get there." Phone
rang off the wall. It better be charged back to that contractor.
Merulla:
"Glad to see that Councillor Mitchell has seen the light
with respect to contracting out". Concern about the snow
removal budget and the argument presented in 2001 that privatization
equalled savings through efficiency. Snow removal budget has doubled.
Crockett: For winter control coming into amalgamation 26% was
contracted out and today it is about 28% contracted out.
Merulla
asked for more consulting contract info to include consultants
during amalgamation. "I would like to publicly state that
I would like 1999 and 2000 included as well in the actual transition
board to council and all the consultant costs at that time."
"the breakdown of the consultant costs by company, rationale
and the amount and that goes for the consulting budget as well".
Robertson says they are working on this and refers to January
2003 report as to format. Merulla and Collins disagree because
that report didn't include the supplier or the amounts or the
rationale. Also requested status report on the MFP contract.
Ferguson:
Winter control for 2001, 2002, 2003? Crockett 2003 budget $12M,
spending $20M. $15 budgetted in 2001 and $12M in 2002. Ferguson:
what's five-year average? Crockett: $16M represents 5-year rolling
average, peak is $20M? $4.7 reduction takes us back to about where
we cut it in 2001. But no money in reserve. (So in the "budget"
they called it $20.7M, then they "reduced" this by $4.7M
which are listed as "savings". But the budget in 2003
was only $12M so even with the "reduction" the new budget
figure is $4M HIGHER). Crockett stresses this $16M figure is exposure.
Crockett states that $21M budget would be very small risk but
"nobody funds a winter control program with very little risk,
but they use a viable reserve to protect that and ensure money
is there when it's needed". Figure then changes to $16.7M
as the actual budget this year. Ferguson: price tag on the April
storm last year? Crockett: "Not off the top of my head but
I assume that it was a $1M to $1.5M storm". (This is quite
revealing because the Winter Control budget was more than $8 million
in deficit by the end of 2003, but we now know that only $1.5
million of that came in April. This means when the budget was
passed at the end of March, the winter control people should have
known that we were already over $6M in deficit, but that wasn't
accounted for in the 2003 budget. This is further evidence of
budget fudging last year.)
Ferguson:
What's the total work accommodation bill? Crockett not sure but
$1.1M is unbudgetted till this year. This is raising overtime
budgets. Ferguson: why do we have to provide WA. Isn't that worker
comp's job. Robertson: individual gets compensation, but we have
to fill the service (eg. Fire crews must be certain size). Aggregate
corporately for WA is 2.5M to 3M. "You're seeing it this
year as a big number. In the past we've tried to simply swallow
it, and as I've said it's simply driven the budget so it's artificial
to put in that way." Also important to address it. We'll
be trying to reassign these workers to lower City costs.
McHattie:
Contractual costs of new development, and delay in getting revenues,
and fact that residential growth doesn't pay. Is this an argument
against urban sprawl? Crockett: "If we grow systematically
and intelligently we can minimize the cost of growth. If we do
sporadic growth, for example throw a subdivision up in the middle
of nowhere so to speak, obviously its more costly to provide services
to that location. The whole GRIDS process will try to address
what growth costs and try to take that into account." Insertion
from another staff member that development charges study is underway
and will address this. McHattie notes that this won't cover operating
costs. Crockett intervenes and says they identify the operating
costs of capital projects.
McHattie:
Question on Red Hill Expressway in terms of operating costs. Have
we done the lifecycle costs. Crockett says there have been reports
and can make those available. Collins intervenes and asks Crockett
to clarify if we have included those operating costs in this and
future budgets. Chris Murray "The report is public and will
obviously drive what the future operation and maintenance costs
of the project will be." McHattie asks for true operating
costs both east-west and north-south. We're in tough situation
with companies closing. Need to look at costs before we proceed
further on the expressway. "The world is a different place
with Stelco announcement yesterday, Levi Strauss disappearing,
Camco disappearing, Slater Steel, WestJet. Are we in a different
financial picture than we were just a month ago?" Asks for
info to be provided.
McHattie:
notes function of ESAIG and suggests it may be a model for reducing
consulting costs. Crockett says they tap into info from other
departments. Difficult to do this for environmental assessment
with volunteers.
Braden:
answer later - what does contracting out cost. Great increase
in cost of doing business between contracting out and not contracting
out? What percent is cost of employee related costs rising? Crockett
"We're obviously being consistent with corporate recommendations".
9.3%. Included is $1.1M for work accommodation.
Pearson:
phantom revenues over the years? Crockett: largely within operations
and maintenance. "Since 2001 we've identified a series of
revenues which were overstated within budgets in order, for whatever
reasons, in terms of revenues expected, whether it be in relation
to revenue for facility rentals, cemetery fees, those sorts of
things, advertising revenues", and we've tried to identify
those and correct them "so we don't have a revenue that artificially
suggests our budget balances when it doesn't because we are not
going to realize those revenues."
Collins:
are overtime costs included in budgets, and how much? Total change
is $693K, total is $2.9M overall. Significant component in transit
and $200K in winter control. Transit overtime hours on mechanics
side because we've reduced number of mechanics. Collins: service
impact of freezing overtime excluding winter control? Crockett
doesn't know.
Collins:
Do energy costs incorporate April increases? Crockett: Yes. During
2003 budget discussions rolled back energy costs of traffic signals
by $300K "and we in fact went $300K over budget"
Collins:
we only start 85% of capital projects planned. Would there be
savings if we only budgetted for what we realistically are going
to complete? Crockett downplays this, "it's not a straight
relationship". Collins: can you provide a scenario if we
let fewer contracts and what the savings would be. Crockett says
it will affect the consulting side more than staff side "simply
because we use consultants not only for expertise but also for
volume".
Collins:
Municipal act changes affect all municipalities? Crockett: may
affect them differently because some already doing what's now
required. All municipalities will be affected by 'road control'
requirement. Collins asks if other municipalities will show this
as a budget pressure. Crockett doesn't know.
Collins:
How many vacancies? Gapping savings included in 2004 budget? Crockett
No.
Collins:
This is my 9th budget and never seen work accommodation before?
How was it dealt with in the past? Crockett over last 2 years
we've tried to incorporate it.
Presentation
by Chris Murray on Red Hill Valley Project:
"Essentially
we're here for the citizens of Hamilton so they can travel safer
and more cost effectively and address environmental problems in
Red Hill Valley." 6.5 employees. Successes in 2003 include
restarting of construction of valley expressway, finalizing of
technical and summary reports, tolling report, and "we're
implementing a community relations program". Also got government
approvals. "Certainly we had some challenges with respect
to Greenhill Avenue and moving forward that work, but it's underway
and my understanding from the project engineer is that our June
deadline for completion this year seems to be on target. We may
be off by a few weeks." "Of the $19.6M approved in 2003
budget, 78% have been tendered and awarded." "A substantial
amount of work will be awarded this year which will have likely
the greatest impact to the environment, and its critical in meeting
the commitments we have made and the requirements of all the approvals
that we maintain a high degree of control over the consequences
of this project. So in order for us to do that we have developed
and we will be implementing an environmental management plan."
Operational objectives in 2004 for 100% of grading and drainage.
"We expect that within the next 4-6 weeks that we will have
completed the clearing from Mud Street to 2-300 metres south of
Melvin" 75% of creek realignment will be tendered and awarded
this year. QEW work funded 100% by the province "and that
work involves not only the connection of Red Hill to the QEW but
also widening of the QEW which is a bit of a separate issue here."
"There's going to be a substantial amount of work awarded
within the next few months". Basically two contracts one
from Mud to Greenhill, second to Melvin. These include 75% of
creek realignment as well as the portion of the CSO pipe. "In
the fall of this year we will be awarding the contract for the
Barton Street interchange works which includes the Rennie Street
landfills works and that will be going this fall." The budget
presented was only for operation of the office and it shows a
17.8% increase (from $368K to $496K).
Cost to complete is $139.1 M with City paying $75.6 and province
paying $63.5M (plus what they pay at the QEW). Graph presented
shows that this year they expect to tender and award $88.9M in
contracts. City portion this year is $17.9M and $15.0M from province.
Overhead notes that unit costs are rising and "increased
legal and security expenses". Murray says "as well as
the kinds of challenges we have faced in the past and we don't
believe they'll go away entirely and the need for legal support
in order to address matters that get raised from time to time
by people who don't support the project, so that's something that's
difficult to target but nonetheless I believe it's something that
we all have to bear in mind because it will probably continue
on as this project moves forward."
McCarthy:
Is the $75.6 million required this year? Murray: No for 2003-2007.
This year is for $17.9M.
McHattie: Cost of QEW. Murray: Estimate is in the order of "about
$60-65 million". This is in addition to provincial support
for valley portion. McHattie: total cost of project? Murray: total
$399M. McHattie: lifecycle costs, what do they add to costs. Murray:
$399M to build the project. Ongoing costs additional. "The
report that's on the web does address the longterm lifecycle costs
of the facilty, both with it and without it. It does look at the
lifecycle costs of structures, and does give us good information
about funds that need to be set aside to make sure that the maximum
amount of benefit can be achieved from the facility. So that is
in that report." McHattie: can you use your personal knowledge
to calculate the total cost? Murray: lifecycle calcualed over
75 years "but doesn't come to my mind at this moment, but
certainly is a figure that is publicly known". McHattie:
Does this include spinoff costs such as servicing lands. Murray:
info is in other reports. "The cost-benefit report looked
at the infrastructure that's being built, and when we say infrastructure,
we mean not just the road but certainly the maintenance of the
stormwater management system as well as the creek, and I think
we recognize that whether you build this road or not, the creek
is facing a number of problems that should be addressed in any
event. So that was also factored into the cost figures that the
report reports."
McHattie:
have to make serious decisions on budget and "being quite
shaken over the past month over the revelations of industries
being in serious trouble in this City, I just have to ask if these
costs can be brought together in one report instead of having
to go across a number of reports to try and determine what the
assumptions are under each section of costs. It's very difficult
to do that, for me, and certainly for the public as well as they
participate in our budget discussions." "I need to see
these costs because this is the biggest project in our history,
it's going to influence us into the ensuing decades and it's going
to drive some of our capital costs". Asks for all costs to
be brought together, perhaps even including ecological costs.
Otherwise can't respond properly to taxpayers. "Perhaps time
to at least slow down and perhaps postpone the project".
Collins asks if he wants a new report, or just all the other reports.
McHattie: consolidation of costs, the big picture. Crockett: all
staff costs are incorporated into capital costs of project. There's
three reports. It's not a simple task pulling those reports together.
You can't just add them together. You need the context of each
of the reports in order to understand the numbers in them. Asks
for further direction. Collins: perhaps summarizing the costs.
McHattie: "what are the real costs and I would hope all councillors
would be interested in what those real costs are". Crockett
says they will attempt to pull together an executive summary.
McCarthy:
asked question of Rinaldo, what are tax implications this year
of not doing Red Hill and he's written back $1.7M? Also issue
of hydro funds. Crockett notes that $1.7M is capital financing
costs versus the actual capital outlay costs.
Braden:
2-3 weeks ago asked about mounds and got commitment that I would
get an answer that week. How come? Crockett: it came out this
week, delayed by legal issue on documentation provided with media
release. Braden: If there's a good reason, should have been told.
"And I don't read the paper, almost religiously now, because
I just don't find it's very accurate".
Braden:
Employee related expenses up 17%. Justification? Murray: "It's
really a combination of matters such as merit increases, and in
this particular case there was an anomoly where one of the staff
was pegged lower than what their salary range should have been,
and so it's addressing that gap between what was pegged last year
and this year."
Braden:
Concerned with costs, "which seems to be a running target"
but also with benefits. "Given the budget this year, in which
we're intending to spend up to $180M more than we're taking in;
so in simple numbers spending an extra half million dollars per
day, each and every day, more than we're taking in. The expectation
of this road becomes more important. I think the other day Councillor
Merulla said the water and sewer contract might be the biggest
project we're undertaking but it's limited time and it only 10
years. This one is sort of for keeps. I'd like to see in simple
plain English what the expectations are, and there has to be a
temporal context to this. The Hemson study which I've asked to
be brought up so I can question him in the next two weeks, it
talks about a sort of normative perspective in which if everything
goes right, this is what's supposed to happen. That's sort of
if you build it they will come. We really need to know what do
we really think's going to happen and here's the controversy,
the thing that's confusing. Our director of Economic Development
is saying (last year) that we've got a ten-year window of opportunity
for those lands on the mountain - and I think he means the airport
lands but he might mean the North Glanbrook lands as well - we
got now a nine year window of opportunity to get those things
going. And the road is seen by some people as one of the important
pieces of this puzzle. But our new budget says that we're not
going to service that land until 2007 and 2008. So for more than
half of this ten year window of opportunity we're sort of holding
our breathe and saying there isn't going to be any growth. So
that's a real problem, sending out confusing messages. If you
give those to the new councillors they'll be as confused as I
am. The second thing those studies say is that the employment
lands that I've just mentioned are going to provide 65% of all
the new growth in employment lands, including Brownfield development
and Ancaster. 65% of all those jobs are going to be in employment
lands from 2001-2021. Again for a third of that time frame we're
agreeing that we're going to have no growth at all. So somehow
the job rate is going to go through the roof, in the future, for
some reason that nobody can explain. It's getting really serious
in the administration now that some of our senior staff members
now are saying to us all, privately and confidentially, we can't
afford almost any project in the capital budget, and they're naming
this project as one we can't afford. So somehow this administration,
and this corporation
" Collins interrupts and says he's
allowing a lot of latitude for editorial comments, not the time
now to debate the budget, but this if for questions. Braden thanks
him for patience and continues: "We need to figure out how
to handle the communication in a way that we understand what we
collectively are trying to achieve here. So costs are a huge issue,
but also there's this issue of expectation and the Hemson report
doesn't do it. Again, it's a normative perspective. It's a this
should happen. Given yesterday's events, we need to wake up."
"The similarity between this corporation and Stelco should
be clear to everybody and we want to avoid the route that Stelco
went yesterday".
Collins:
"Comment made that somewhere in the budget binders that this
project is unaffordable? Did I misunderstand you councillor? Braden
repeats. Jackson asks who on senior staff is saying this.
Ferguson:
Tolls, where does this stand? Murray: Report coming first quarter
of this year. Speaks to cost of implementing a tolling operation,
what kind of potential revenues, also impact on traffic in the
community. There is the real problem of trying to extract a revenue
and then seeing the road not serve the purpose it was supposed
to serve.
LUNCH
BREAK
AFTERNOON
SESSION
|